OUR PROJECTS

SANITATION NETWORK WILL BRING MORE HEALTH TO THE BILLINGS REGION

Execution of works in the sewage sanitary system in sub basins of areas A-F at Billings, Sao Bernardo do Campo city, state of Sao Paulo

Project starting
17/01/2018
%

Ongoing process – August

Expected completion
01/01/2021

ABOUT THE WORK

Program integrates to Environmental Improvement in the area of springs of dam Billings/Sao Bernardo do Campo, formed by trunk collectors, sewage lifting stations , reinforced lines, collecting networks, residential and interconnections

Client: Sabesp   

 

OUR PROJECT IN NUMBERS

ico_valor

Contract value
R$ 89.346.257,95
See contract

Without additionals

ico_fonte

Resource
Companhia de Saneamento Básico do Estado de São Paulo

ico_grupo

Beneficiaries
250.000

ico_co2

Emission CO2
141 tonnes less of C02 in the atmosphere and preservation 865  trees in august

ico_agua

Reuse of water
0 liters saved in august

ico_recycle

Waste management
36.000 tonnes of waste for the recycling cooperative in august

ico_profissional

Hired
20 professionals

ico_call-center

Ombudsman
3 call received

ico_profissional

Number of professionals

ico_acidente

Frequency rate of occupational accidents

caution

Highest risk accidents rate

PROJECT LIVE

LOCATION

OUR PROJECTS